Project Task Assignments - February 2025
This document outlines active and graveyard tasks for the MultiDev implementation project. Active tasks are currently in progress, while graveyard tasks are deprioritized but assigned for future pickup when resources become available.
Team Assignments
- Matt Kersey
- Norma
- Natasha
- Suzen
- Jaleel & Travis
- Art
Active Tasks
Shipping Tool Implementation
- Priority: High
- Due Date: 2/28/2025
- Description: Complete end-to-end testing of shipping tool, document configuration issues. Focus on error appearing on every other click.
UOwn/Progressive Configuration
- Priority: Medium
- Due Date: 2/28/2025
- Description: Work with contractor to outline process and update vendors with flow for production credentials.
Petty Cash Transaction Fix
- Priority: Medium
- Due Date: 2/28/2025
- Description: Investigate and resolve error in petty cash transactions for supplier. Document solution for accounting team.
Graveyard Tasks
Bank Rec End-to-End Testing
- Priority: Low
- Due Date: 3/15/2025
- Description: Complete comprehensive testing with large batch of transactions once initial configuration is stable.
Active Tasks
CSS Data Page Integration
- Priority: High
- Due Date: 4/1/2025
- Description: Work with Alban at Data Page to validate file format and mapping. Focus on understanding output mapping to CSS.
Customer API Updates
- Priority: High
- Due Date: 3/20/2025
- Description: Review and document specifications for insurance field updates and associated changes.
Graveyard Tasks
Store Portal Customer Edits
- Priority: Low
- Due Date: 3/31/2025
- Description: Address flow of customer edits from Store Portal to CSS. Can be handled manually for now.
Recency Testing
- Priority: Low
- Due Date: 3/15/2025
- Description: Follow up testing of recency calculations, review output against contractual requirements.
Active Tasks
Quality Gold Dropship Integration
- Priority: High
- Due Date: 2/28/2025
- Description: Resolve parsing errors in remaining 5% of catalog. Test publishing to web with focus on EAV attributes.
Inventory Simulations
- Priority: High
- Due Date: 2/28/2025
- Description: Complete training on min-max calculations. Test uploading data for single subclass to model and SKU level.
Graveyard Tasks
Product Attributes Validation
- Priority: Medium
- Due Date: 3/15/2025
- Description: Validate inventory catalog publishing to web for attributes after data conversion completion.
Active Tasks
Payment Types Testing
- Priority: High
- Due Date: 2/28/2025
- Description: Coordinate with Shopify team to test Klarna/Affirm/PayPal integration once implemented.
Returns and Discounts Validation
- Priority: High
- Due Date: 2/28/2025
- Description: Complete validation through Cash Z and Bank Rec. Identify cause of non-updating orders.
Graveyard Tasks
Insurance Application Flow
- Priority: Medium
- Due Date: 3/15/2025
- Description: Validate FedEx test insurance and third-party insurance carrier integration.
Active Tasks
Base Data Conversion
- Priority: Critical
- Due Date: 2/28/2025
- Description: Complete remaining fields in base data conversion. Coordinate with Art on context and methods.
Graveyard Tasks
Incremental Data Conversion
- Priority: Medium
- Due Date: 3/15/2025
- Description: Plan conversion process for transfers, invoices, POs, web orders, and backorders.
Active Tasks
Security Matrix Review
- Priority: High
- Due Date: 2/21/2025
- Description: Review security roles and access functionality with David B. Provide final approval for implementation.
Graveyard Tasks
CSS Batch Testing Support
- Priority: Medium
- Due Date: 3/15/2025
- Description: Support batch testing for calc and roll after data conversion completion.
Escheatment Process Documentation
- Priority: Low
- Due Date: 3/31/2025
- Description: Document comprehensive escheatment process including prenote period and state requirements.
Implementation Guidelines
When presenting these assignments:
- Start with overview of task organization (5 min)
- Review active assignments by person (15 min)
- Explain graveyard task concept (5 min)
- Address questions and adjustments (5 min)
Task Management in Asana
- Create sections for "Active" and "Graveyard" tasks
- Set due dates as specified
- Include full descriptions provided
- Add dependencies as task relationships
- Configure custom fields for priority levels
Graveyard Task Guidelines
Graveyard tasks should only be pulled when:
- Team member has unexpected bandwidth
- All dependencies are resolved
- Task activation won't impact critical path items
- Business priorities haven't changed
Weekly Review Process
- Review active task progress
- Assess resource availability
- Evaluate graveyard task priorities
- Update dependencies and timelines
- Adjust assignments as needed
Critical Dependencies
graph TD
A[Base Data Conversion] --> B[CSS Batch Testing]
A --> C[Product Attributes]
D[Security Matrix] --> E[User Management]
F[Payment Types] --> G[Returns Validation]
Success Metrics
Category | Metric | Target |
---|---|---|
Active Tasks | Completion Rate | 90% by due date |
Graveyard Tasks | Activation Rate | Max 1 per resource |
Dependencies | Blocking Time | < 2 days |
Communication | Status Updates | Weekly |